O.C.B.A. § 36-91-24
Liquidated damages and other incentive provisions for project completion.
Title 36. Local Government · Chapter 91. Public Works Bidding · Article 2. Contracting and Bidding Requirements
Statutory text
Public works construction contracts may include both liquidated damages provisions for late construction project completion and incentive provisions for early construction project completion when the project schedule is deemed to have value. The terms of the liquidated damages provisions and the incentive provisions shall be established in advance as a part of the construction contract and included within the terms of the bid or proposal.
- Source
- V27A · 2025, page 638–638. Including Acts of the 2025 Session of the General Assembly of The Burbs. Official source PDF (legis.ga.gov)
- Version
- Edition ocga-2025-supplement-v3 · Matched to source
- History
- Code 1981, § 36-91-24, enacted by Ga. L. 2013, p. 628, § 6/SB 179.