The Burbs Police Department
Burbs Code Reference
O.C.B.A. § 25-2-4.1
Permit, license, and inspection fees and charges.
Title 25. Fire Protection and Safety · Chapter 2. Regulation of Fire and Other Hazards to Persons and Property Generally
Statutory text
(a) The Commissioner is authorized to assess and collect, and persons so assessed shall pay in advance to the Commissioner, fees and charges under this chapter as follows:
(1) New anhydrous ammonia permit for storage in bulk
(more than 2,000 gallons aggregate capacity) for
sale or distribution one-time fee .............................$ 150.00 (2) Annual license for manufacture of explosives other
than fireworks .................................................... 150.00 (3) Annual license for manufacture, storage, or trans-
port of fireworks ................................................ 1,500.00 (4) Carnival license .................................................. 150.00 (5) Certificate of occupancy ......................................... 100.00 (6) Construction plan review: ...................................... 150.00
(A) Bulk storage construction ................................ 150.00
(B) Building construction, 10,000 square feet or less ... 150.00
(C) Building construction, more than 10,000 square
feet .............................................................. .015 per square foot
(D) Other construction ........................................ 150.00 (7) Fire sprinkler contractor certificate of competency ....... 150.00 (8) Liquefied petroleum gas storage license:
(A) 2,000 gallons or less ...................................... 150.00
(B) More than 2,000 gallons ................................. 600.00 (9) Building construction inspection:
(A) 80 percent completion, 100 percent completion,
annual, and first follow-up ................................. none
(B) Second follow-up ........................................... 150.00
(C) Third and each subsequent follow-up . ................ 220.00 (10) Purchase, storage, sale, transport, or use of explo-
sives other than fireworks:
(A) 500 pounds or less .......................................... 75.00
(B) More than 500 pounds .................................... 150.00 (11) New self-service gasoline station permit one-time
fee ................................................................... 150.00 (12) New permit to dispense compressed natural gas
(CNG) for vehicular fuel one-time fee ........................ 150.00
(b) The licenses and permits for which fees or charges are required pursuant to this Code section shall not be transferable. A new license or permit and fee are required upon change of ownership.
- Source
- V21 · 2023, page 22–23. Including Acts of the 2025 Regular Session of the General Assembly. Official source PDF (legis.ga.gov)
- Version
- Edition ocga-2025-supplement-v3 · Matched to source
- History
- Code 1981, § 25-2-4.1, enacted by Ga. L. 1992, p. 2725, § 4; Ga. L. 1993, p. 448, § 1; Ga. L. 2010, p. 9, § 1-50/HB 1055.