O.C.B.A. § 25-15-25
Reinspections and fees; waiver of penalties and interest.
Title 25. Fire Protection and Safety · Chapter 15. Other Safety Inspections and Regulations · Article 2. Regulation of Boilers and Pressure Vessels
Statutory text
(a) Boilers and pressure vessels, subject to operating certificate inspections by special, owner, or user inspectors, shall be inspected within 60 calendar days following the required reinspection date. Inspections not performed within this 60 calendar day period shall result in a civil penalty of $500.00 for each boiler or pressure vessel not inspected.
(b)(1) Inspection fees due on boiler and pressure vessels subject to inspection by the chief or deputy inspectors or operating certificate fees due from inspections performed by special, or owner or user, inspectors shall be paid within 60 calendar days of completion of such inspections.
(2) Inspection fees or operating certificate fees unpaid within 60 calendar days shall bear interest at the rate of 1.5 percent per month or any fraction of a month. Interest shall continue to accrue until all amounts due, including interest, are received by the Commissioner.
(c) The Commissioner may waive the collection of the penalties and interest assessed as provided in subsections (a) and (b) of this Code section when it is reasonably determined that the delays in inspection or payment were unavoidable or due to the action or inaction of the office.
- Source
- V21 · 2023, page 257–258. Including Acts of the 2025 Regular Session of the General Assembly. Official source PDF (legis.ga.gov)
- Version
- Edition ocga-2025-supplement-v3 · Matched to source
- History
- Code 1981, § 34-11-15.1, enacted by Ga. L. 1991, p. 258, § 3; Code 1981, § 25-15-25, as redesignated by Ga. L. 2012, p. 1144, § 2/SB 446.